6.4 Summary Comparison Matrix
Table 8: Pocahontas County Data Center Suitability - Comparative Matrix
Requirement | Ideal Benchmark | Pocahontas County Status | Assessment | Key Considerations/Mitigation Needs |
Power Cost | Competitive (<$0.0X/kWh target) | Potentially very competitive (~5.2¢/kWh avg for large users reported, plus incentives) 32 | Advantage | Confirm final rate with Mon Power including all surcharges & tariffs (K/LP/MBR). |
Power Reliability/Capacity | High capacity (Multi-MW), N+1 Redundancy, High Reliability (SAIDI/SAIFI) | Capacity/Redundancy at specific sites unconfirmed. Single provider (Mon Power). Upgrades ongoing. 18 | Challenge/Uncertain | CRITICAL: Verify site-specific capacity, reliability metrics, and redundancy options (dual feeds?) with Mon Power. |
Network Connectivity | Diverse, redundant, high-capacity, low-latency fiber | Backbone builds ongoing but site-specific availability/diversity uncertain. Rural latency. NRQZ limits wireless. 45 | Significant Challenge | CRITICAL: Commission detailed network study (routes, providers, latency, cost/timeline for builds). Assess NRQZ impact on design. |
Climate/Cooling | Temperate, enables free cooling | Favorable climate for economization. Moderate temps, high humidity. Adequate precipitation. 49 | Advantage | Design for humidity control. Verify water source adequacy if liquid cooling planned. |
Natural Disaster Risk | Low risk (Flood, Seismic, Severe Weather) | Low seismic. Moderate flood (site-specific, maps updating). Moderate severe storm/winter weather. Very low tornado. 69 | Neutral/Mixed | CRITICAL: Site-specific flood analysis using latest FEMA preliminary data. Design for wind/snow loads. |
Land/Zoning | Sufficient acreage (~40+), Favorable zoning, Reasonable cost | Acreage available in industrial parks. State law (HB 2014) preempts local zoning. Costs likely favorable. 97 | Advantage | Verify site suitability (geotech, environmental). Navigate potential local friction from state preemption. |
Workforce | Skilled technical labor pool, Training resources, Quality of Life | Very limited local skilled pool. Low wages. Regional draw needed. Training resources exist. Housing shortage. 111 | Significant Challenge | Develop regional recruitment strategy. Partner with New River CTC for training. Address housing (leverage BUILD WV). |
Incentives/Taxes | Strong state/local incentives, Low tax burden | Excellent state data center incentives (property/sales tax). Very low base property tax rates. HB 2014 diverts local tax revenue. 107 | Strong Advantage | Maximize state incentives. Manage local relations regarding tax distribution. |
Scalability | Room for expansion (site, power, network) | Industrial parks offer adjacent land. Power/Network scalability needs verification. 96 | Neutral/Uncertain | Confirm utility/network provider ability to scale capacity with project growth. |
Security | Physically secure location, Compliance capable | Rural location offers some inherent security. Requires standard physical security investment. Compliance depends on facility design/ops. 5 | Neutral | Implement robust physical security measures. Design for compliance needs. |