Suggestion: A Data Center for Pocahontas County


 

 A Data Center for Pocahontas County

6.4 Summary Comparison Matrix

Table 8: Pocahontas County Data Center Suitability - Comparative Matrix


Requirement

Ideal Benchmark

Pocahontas County Status

Assessment

Key Considerations/Mitigation Needs

Power Cost

Competitive (<$0.0X/kWh target)

Potentially very competitive (~5.2¢/kWh avg for large users reported, plus incentives) 32

Advantage

Confirm final rate with Mon Power including all surcharges & tariffs (K/LP/MBR).

Power Reliability/Capacity

High capacity (Multi-MW), N+1 Redundancy, High Reliability (SAIDI/SAIFI)

Capacity/Redundancy at specific sites unconfirmed. Single provider (Mon Power). Upgrades ongoing. 18

Challenge/Uncertain

CRITICAL: Verify site-specific capacity, reliability metrics, and redundancy options (dual feeds?) with Mon Power.

Network Connectivity

Diverse, redundant, high-capacity, low-latency fiber

Backbone builds ongoing but site-specific availability/diversity uncertain. Rural latency. NRQZ limits wireless. 45

Significant Challenge

CRITICAL: Commission detailed network study (routes, providers, latency, cost/timeline for builds). Assess NRQZ impact on design.

Climate/Cooling

Temperate, enables free cooling

Favorable climate for economization. Moderate temps, high humidity. Adequate precipitation. 49

Advantage

Design for humidity control. Verify water source adequacy if liquid cooling planned.

Natural Disaster Risk

Low risk (Flood, Seismic, Severe Weather)

Low seismic. Moderate flood (site-specific, maps updating). Moderate severe storm/winter weather. Very low tornado. 69

Neutral/Mixed

CRITICAL: Site-specific flood analysis using latest FEMA preliminary data. Design for wind/snow loads.

Land/Zoning

Sufficient acreage (~40+), Favorable zoning, Reasonable cost

Acreage available in industrial parks. State law (HB 2014) preempts local zoning. Costs likely favorable. 97

Advantage

Verify site suitability (geotech, environmental). Navigate potential local friction from state preemption.

Workforce

Skilled technical labor pool, Training resources, Quality of Life

Very limited local skilled pool. Low wages. Regional draw needed. Training resources exist. Housing shortage. 111

Significant Challenge

Develop regional recruitment strategy. Partner with New River CTC for training. Address housing (leverage BUILD WV).

Incentives/Taxes

Strong state/local incentives, Low tax burden

Excellent state data center incentives (property/sales tax). Very low base property tax rates. HB 2014 diverts local tax revenue. 107

Strong Advantage

Maximize state incentives. Manage local relations regarding tax distribution.

Scalability

Room for expansion (site, power, network)

Industrial parks offer adjacent land. Power/Network scalability needs verification. 96

Neutral/Uncertain

Confirm utility/network provider ability to scale capacity with project growth.

Security

Physically secure location, Compliance capable

Rural location offers some inherent security. Requires standard physical security investment. Compliance depends on facility design/ops. 5

Neutral

Implement robust physical security measures. Design for compliance needs.